Consumer Commission Orders Livspace to Refund 71.62 Lakh Over Mumbai Home Renovation

By Aru06

Summary

The Maharashtra State Consumer Disputes Redressal Commission has directed Livspace India Private Limited to refund ₹71,62,004 to a Mumbai homeowner after finding deficiency in service and unfair trade practices in the renovation of his Goregaon apartment. In its order dated 5 November 2026, the commission also directed the company to pay simple interest at 9% a year on the refund, calculated from 1 September 2024 until the amount is realised. It awarded a further ₹1 lakh as compensation and ₹50,000 towards litigation costs. The case proceeded ex parte because Livspace did not appear before the commission.

Published on

4 min read3 views
A Mumbai consumer commission ordered a ₹71.62 lakh refund in a home renovation dispute involving Livspace.

An illustrative unfinished kitchen reflects the concerns about workmanship, materials and delays examined in the Mumbai renovation case. The commission ordered a refund of ₹71.62 lakh, with interest and separate compensation and costs.

The Maharashtra State Consumer Disputes Redressal Commission has directed Livspace India Private Limited to refund ₹71,62,004 to a Mumbai homeowner after finding deficiency in service and unfair trade practices in the renovation of his Goregaon apartment.

In its order dated 5 November 2026, the commission also directed the company to pay simple interest at 9% a year on the refund, calculated from 1 September 2024 until the amount is realised. It awarded a further ₹1 lakh as compensation and ₹50,000 towards litigation costs.

The case proceeded ex parte because Livspace did not appear before the commission. The findings were made after consideration of the complainant's evidence, which the commission said remained unrebutted.

What did the homeowner complain about?

Complainant Deepak Ruiya engaged Livspace for interior design and renovation work at his residential apartment. The commission recorded that he paid ₹71,62,004 for the work.

According to the order, the original handover date was 1 July 2024 and was later extended to 1 September 2024. The commission found that the project remained incomplete beyond the extended deadline.

The homeowner also alleged that materials and kitchen components supplied during execution differed from those promised. The commission accepted the evidence before it and found that substitutions of promised materials and products amounted to an unfair trade practice.

Read the commission's order here -> Deepak Ruiya vs Livspace India Private Limited.

Safety concerns and project management

The commission recorded serious concerns about the condition of the apartment, including uninsulated electrical wires behind bed panels. It also recorded that a kitchen shutter fell on the complainant's wife on 2 January 2025.

The commission examined the project's management as well. It found that changes in designated personnel and project managers contributed to poor oversight and delays.

The order should be read in the context of the proceedings: Livspace did not appear before the commission, and the complainant's affidavit and documentary evidence were not challenged by the company in that proceeding.

A report based on the order summarises the findings and the relief granted -> Epitome of negligence: Consumer panel orders firm to refund Rs 71.6 lakh for shoddy flat renovation.

What did the commission order?

The commission partly allowed the complaint and directed Livspace to pay:

  • ₹71,62,004 as a refund.
  • Simple interest at 9% per year on that amount from 1 September 2024 until realisation.
  • ₹1 lakh as compensation.
  • ₹50,000 towards litigation costs.

Some reports describe the amount as approximately ₹87 lakh. The order itself specifies a principal amount, interest continuing until realisation, and separate sums for compensation and costs. The final amount therefore depends on the date of payment.

The order does not, by itself, establish that the homeowner has received payment. The status of any appeal or subsequent proceedings could not be independently verified for this article.

Why the case matters

Interior projects often involve several decisions beyond the overall price, including material specifications, component ranges, changes during execution, payment schedules and handover dates.

The commission's findings show how those details became central to this particular dispute. They also highlight the importance of the records placed before the commission, including the contract, payment receipts, correspondence, photographs and survey material.

The outcome is specific to the evidence and circumstances of this case. It does not establish that every delay or material change in a renovation amounts to an unfair trade practice.

Sources

Click an article title to view the source.

Evidence Caveats

The article is based on the commission's order available through Indian Kanoon and the cited PTI report. A certified copy was not independently obtained. The case proceeded ex parte, and the company's defence was not presented before the commission in that proceeding. No subsequent appeal, payment or company response could be independently verified for this article.

What information would you want an interior service provider to document before work begins, and how should changes be approved during the project? Share your experience or questions in the attached forum discussion.

TatvaOps

From TatvaOps

Home Renovation

Renovating your space?

Lock scope, compare quotes, and pay only after milestone approval on TatvaOps.

Free quotes · Verified contractors · tatvaops.com

Discuss this article

Join the conversation

Continue this discussion on Forums. A board named like this Radar article is filed under Radar.

Was this helpful?

Let us know what you think