Construction toolkit
Materials from area, mix and wall volume
A residential RCC rule of thumb, then a nominal concrete mix and a brick count. Use it to sanity-check a contractor’s quantities before you freeze a quote.
Indicative only. Design, wastage and your city change the order.
Cement
480 bags
50 kg bags, before wastage
Steel
4,800 kg
TMT, framed RCC thumb rule
Sand
1,440 cft
Rounded up
Aggregate
1,620 cft
Rounded up
Build cost
₹28,80,000
1,200 sq ft × ₹2,400
Your rate
₹2,400 / sq ft
The contractor number you entered
Built-up area
How the thumb rule is applied
- 1Cement1,200 sq ft × 0.4 bags, rounded up480 bags
- 2Steel1,200 sq ft × 4 kg, rounded up4,800 kg
- 3Sand1,200 sq ft × 1.2 cft, rounded up1,440 cft
- 4Aggregate1,200 sq ft × 1.35 cft, rounded up1,620 cft
- 5Add 10% wastage before you orderSite cutting, spillage and breakage. Confirm with your engineer.× 1.10
- 6Build cost at your rate1,200 × ₹2,400 per sq ft₹28,80,000
Build cost by contractor rate
For 1,200 sq ft. Your rate, ₹2,400 / sq ft, prices the house at ₹28,80,000.
Concrete mix
Dry volume is wet volume × 1.54. One cubic metre of cement is about 28.8 bags of 50 kg.
M20 for 10 m³
- 1Dry volume10 × 1.5415.40 m³
- 2CementDry volume × 1 / 5.5 × 28.8 bags81 bags
- 3SandDry volume × 1.5 / 5.54.20 m³
- 4AggregateDry volume × 3 / 5.58.40 m³
Brick masonry
Modular brick with 10 mm mortar: 500 bricks per cubic metre of wall.
4,000 bricks